6、A customer is surprised about a change made to a deliverable.The project manager explains that this change was communicated via email,and that there is a possibility that the em ail has not yet been read.What should the project manager h ave done differently?
客戶對某個可交付成果的變更感到驚訝.項目經理解釋說,這一變更是通過電子郵件溝通的,客戶有可能還沒有閱讀電子郵件.項目經理事先應該采取哪—項不同做法?
A、Ensured that the communication cycle was complete d,and asked the customer to confirm receipt of the information確保已完成溝通循環,并要求客戶確認已收到信息
B、Sent a follow-up email to determine if the customer re ad the first email,and obtained a read confirmation發送一封跟進電子郵件已確定客戶是否閱讀了第一封電子郵件,并獲得已閱讀確認
C、Called,rather than emailed,the customer with all details,and asked them to send a confirmation給客戶打電話(而不是通過電子郵件)告訴客戶所有詳細信息,并要求他們發送確認信
D、Developed the communications management plan制定溝通管理計劃
7、根據項目計劃,項目的狀態如下∶按每小時28美元的勞動費率,工作1000小時,計劃花費28000美元。監控成本時,項目經理確定成本績效指數為0.8。項目的實際成本為40000美元。項目的進度偏差是多少?()
A、-12000元
B、4000美元
C、5600美元
D、12000美元
8、一個項目可交付成果延期并錯過了截止日期,團隊領導為這些問題責備初級團隊成員。項目經理應該怎么做?
A、與該團隊領導召開一對一的會議
B、執行風險評估
C、與初級團隊成員協商進度計劃
D、與同事討論,識別根本原因
9、The asphalt highway project that the project manager is managing is 50%complete.The PM planned on having 4,000 square yards of asphalt placed by now,but in actuality.They've finished placing 8,000 square yards.The estimated cost forth is work was$1 per square yard.The actual cost for this work is$8,000.
What does this tell the project manager?
項目經理管理的瀝青公路項目已完工50%。項目經理原本計劃到現在為止鋪4000平方碼的瀝青。而實際上他們已經鋪完了8000平方碼。這項工作的估算成本為1美元/平方碼,實際花費8000美元。這告訴項目經理什么信息?()
A、EV is 2.
B、SPI is 2.
C、SPI is 0.50.
D、SV is 0.50
10、敏捷團隊完成了產品開發階段,并核實所有測試均已通過,但客戶報告對質量和性能不滿意。若要避免這種情況,敏捷項目團隊應該在產品發布之前做什么?
A.召開一次回顧會議,核實項目可交付成果
B.執行對所有需求的評審
C.獲得項目發起人的批準
D.在計劃的演示中,收集項目干系人反饋