PMP備考每日試題(230318)
每期慧翔天地小編都會附上5~10道PMP?綜合測試題,以幫助大家達到練習的效果,本期PMP試題答案會附加在下一期的結尾。大家如果想了解2023年PMP?考試報考流程、PMP@報考時間及報考要求、PMP?報考費用、PMP?考試地點、PMP?成績查詢、PMP?報考資格測評等等均可訪問站內進行了解。
PMP備考刷題交流群:667625965(點擊一鍵加群)
1、A project manager is asked to perform a cost benefit analysis for two potential projects.Project A costs US$1.2 billion,wit h potential benefits of U S$6 billion and future operating cos ts US$1.5 billion.Project B costs US$1.4 billion,with potential benefits of US$7 billion and future operating costs US$1 billion.Which project should the project manager recommend?
項目經理被要求對兩個潛在項目進行成本效益分析。項目A成本為12億美元,潛在收益為60億美元,未來的運營成本為15億美元。項目B成本為14億美元,潛在收益為70億美元,未來的運營成本為10億美元。項目經理應該推薦哪個項目?
A、Project B:the potential benefits minus the costs to implement are greater than the same calculation for project A項目B,因為潛在效益減去執行成本所得的值大于項目A所得值
B、Project A;the cost to implement is less than project B項目A,因為執行成本低于項目B
C、Project B;the potential benefits minus the implementation and future operating costs are greater than the same calculation for project A項目B,因為潛在效益減去執行成本和未來運營成本所得的值大于項目A所得值
D、Project A;the potential benefits plus the future operating costs are less than the same calculation for project B項目A,因為潛在效益加上未來運營成本所得的值小于項目B所得值
2、A key project stakeholder requests that a team member make a small modification to a feature.The team member decides t he change could be incorporated in a short time frame.The team member implements the change without informing the project manager.During validate scope,the project manager finds out about the team member's modification.After conducting a detailed analysis,the project manager finds that the tea m member's initial analysis was incomplete and the modification needed additional effort and time.What should the project manager do next?( )
一名關鍵的項目相關方要求團隊成員對某項功能進行了一些小修改。團隊成員認為該變更所涉及的時間很短。因此在沒有通知項目經理的情況下,就實施了變更。在確認范圍期間,項目經理發現了團隊成員的修改。在執行詳細的分析之后,項目經理發現團隊成員的初步分析并不完整。這項修改需要投入額外的人工量和時間。項目經理下一步應該怎么做?()
A、Proceed to the next stage by revoking the change incorporated by the team member and informing the stake holder accordingly.撤銷團隊成員所包含的變更,執行下一個階段,同時通知項目相關方。
B、Discuss with the stakeholder the importance of the hange,highlighting the further impact on the cost and schedule.If the stakeholder insists on including the change,report the change to the change control board for approval.與項目相關方討論該變更的重要性,強調對成本和進度的進一步影響。如果項目相關方堅持要將該變更包含在內,向變更控制委員會報告該變更,以獲得批準。
C、Inform the stakeholder about the further impact on co st and schedule due to the change.In the current stage of the project,the change cannot be included.通知項目相關方由于變更對成本和進度的進一步影響。在目前項目所處的階段,不能將變更包含在內。
D、Escalate to the sponsor about the stakeholder directly interacting with the team member.將項目相關方直接與團隊成員交流一事上報給項目發起人。
3、完成項目規劃階段之后,項目經理安排了一次階段收尾會議。在這次會議上,會發生什么事情?
A、項目經理審查項目團隊成員的績效
B、高級管理層分析項目經理的績效
C、審查項目可交付成果,并做出繼續項目的決定
D、記錄項目的經驗教訓,項目收尾
4、負責商業交易的高級經理識別到控制交易風險的某個系統需求。高級經理起草了發放項目資金所需的商業文件,要求項目經理立即開始項目。項目經理首先應該怎么做?
A、識別相關方
B、制定項目章程
C、定義項目范圍
D、編寫項目管理計劃
5、項目經理和團隊在獲取資源的過程中,可能采用決策技術來選擇資源,一般選擇標準包括:
A、可用性、獨特性、時間要求
B、可用性、成本、個人風格
C、可用性、成本、能力
D、可用性、獨特性、個人風格
(230317)答案
6、B
7、D
8、A
9、A
10、D