6、Two coworkers are developing a project task together.Coworker 1 prefers to write down ideas and thoughts before doing the actual work.Coworker 2 has a direct work style.The difference in their personal work styles creates a conflict between them and affects their performance on project activities.Who is responsible for resolving this issue?
兩個(gè)同事正在一起開(kāi)發(fā)一個(gè)項(xiàng)目任務(wù)。同事1喜歡在做實(shí)際工作之前寫(xiě)下創(chuàng)意和想法。同事2有直接的工作作風(fēng)。他們個(gè)人工作風(fēng)格的差異造成了他們之間的沖突,影響了他們?cè)陧?xiàng)目活動(dòng)中的表現(xiàn)。誰(shuí)負(fù)責(zé)解決這個(gè)問(wèn)題?
A、Project manager項(xiàng)目經(jīng)理
B、Human resource manager人力資源經(jīng)理
C、Project sponsor項(xiàng)目發(fā)起人
D、Functional manager職能經(jīng)理
7、制造預(yù)期產(chǎn)品原型供相關(guān)方進(jìn)行實(shí)驗(yàn)和提供反饋后,項(xiàng)目經(jīng)理可完成制定下列哪項(xiàng)?
A、項(xiàng)目章程
B、需求文件
C、項(xiàng)目管理計(jì)劃
D、項(xiàng)目文件
8、The project team has just completed the initial project schedule and budget.The NEXT thing to do is:
項(xiàng)目團(tuán)隊(duì)剛剛完成了項(xiàng)目進(jìn)度和預(yù)算,接下來(lái)該做什么?
A、Begin identifying risks開(kāi)始識(shí)別風(fēng)險(xiǎn) 慧翔天地
B、begin iterations.開(kāi)始漸進(jìn)明細(xì) 慧翔天地
C、determine communications requirements.確定溝通需求 慧翔天地
D、create a bar(Gantt)chart.制作甘特圖 慧翔天地
9、生產(chǎn)某個(gè)項(xiàng)目可交付成果所需的設(shè)備既舊又不可靠,工廠經(jīng)理建議訂購(gòu)一臺(tái)新機(jī)器。工廠經(jīng)理向項(xiàng)目經(jīng)理提交變更請(qǐng)求記錄下列哪項(xiàng)?
A、糾正措施
B、缺陷補(bǔ)救
C、預(yù)防措施
D、更新
10、在項(xiàng)目收尾階段,項(xiàng)目經(jīng)理計(jì)劃開(kāi)展全面的項(xiàng)目宙查,在轉(zhuǎn)移可交付成果并分發(fā)最終項(xiàng)目報(bào)告后,項(xiàng)目經(jīng)理下—步應(yīng)該怎么做?
A、準(zhǔn)備一份采購(gòu)文件
B、執(zhí)行經(jīng)驗(yàn)教訓(xùn)總結(jié)
C、將項(xiàng)目文件和資料存檔
D、獲得項(xiàng)目發(fā)起人的簽署同意
PMP備考每日試題(240210)點(diǎn)擊跳轉(zhuǎn)
(240210)答案
1、C
2、A
3、C
4、C
5、A