PMP備考每日試題(240712)
PMP備考刷題交流群:667625965(點擊一鍵加群)
1、A project manager is working on an internal project that requires a new point of sale(POS)transaction system.The project manager discovers an issue with the system that may not only delay this project,but also a number of other projects dependent upon this system.This issue was not include in the risk register,because previous trials deemed the system free o f flaws Who should the project manager contact about this is sue?
項目經理正在開展一個內部項目,需要一個新的銷售點(POS)交易系統,項目經理發現這個系統有個問題,不僅可能延遲這個項目,而且還會影響到依賴于這個系統的其他一些項目.這個問題未包含在風險登記冊中,因為之前的試驗認為該系統沒有缺陷.項目經理應該聯系誰來解決這個問題?
A、IT department IT部門
B、Sponsors who were affected受影響的發起人
C、Project managers who were affected受影響的項目經理口一
D、Operations team運營團隊
2、一家產品開發公司正在從事一種消費品的工作。在sprint執行期間,一名關鍵干系人無法提供反饋。團隊應在什么時候收集這名干系人的反饋?
A.在部署產品投入生產時
B.在sprint回顧會上
C.盡早
D.在下一次sprint規劃會議上
3、During the last week of the project,a strong storm causes damage and impacts the project's delivery date?What should t he project manager do
在項目的最后一個星期.一場強風暴造成損害并影響項目的交付日期,項目經理應該怎么做?
A、Submit a change request.提交變更請求。
B、Report it to the project sponsors.將其報告給項目發起人。
C、Use the reserve analysis technique.使用儲備分析技。
D、Update the risk register.更新風險登記冊。
4、在規劃范圍管理過程中,你可以使用以下技術來推動本過程的實現,除了:
A、考慮具備相關專業知識的個人或小組的意見
B、通過備選方案分析
C、通過會議
D、借助項目管理信息系統
5、The project has more than 1,000 work packages,and is two years long.It is performing with CPI=1.18 and SPI=0.88.What technique should the project manager use to solve this situation?
項目包括1000多個工作包為期兩年,項目CPI為1.18,SPI為0.88。項目經理應采用何種方法處理該情況?
A、Critical path method關鍵路徑法
B、Resource leveling資源平衡
C、Crashing趕進度
D、PERT PERT
(240711)答案
6、D
7、B
8、C
9、C
10、C