軟考備考每日試題(230814)


每期慧翔天地小編都會(huì)附上5~10道軟考綜合測(cè)試題,以幫助大家達(dá)到練習(xí)的效果,本期軟考試題答案會(huì)附加在下一期的結(jié)尾。大家如果想了解2023年軟考考試報(bào)考流程、報(bào)考時(shí)間、報(bào)考要求、軟考報(bào)考費(fèi)用、軟考成績(jī)查詢、軟考報(bào)考資格測(cè)評(píng)等等均可訪問站內(nèi)進(jìn)行了解。
軟考中高項(xiàng)備考刷題交流QQ群:221801769(點(diǎn)擊一鍵加群)
71、()is the technology that appears to emulate human performance typicaliy by learning,coming to its own conclusions,appearing to understand complex content,engaging in natural dialogs with people,enhancing human cognittive performance(also known as cognittive computing)or replacing people on execution of nonroutine tasks.
A.Cloud service
B.Blockchain
C.Internet of things
D.Artificial intellingence
72、()is a decentralized,distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be altered retroactively without the alteration of all subsequent blocks and the collusion of the network.
A.Cloud service
B.Blockchain
C.Internet of things
D.Artificial intellingence
73、()includes the processes required to ensure that the project include all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.
A.Create scope
B.Project stakeholder management
C.Project scope management
D.Project cost management
74、Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources.The tools and technques is not including().
A.expert judgment
B.analogous estimating
C.requirements traceability matrix
D.three-point estimating
75、()The process of translating the quality management plan into excutable quality activities that incorporate the organization's quality policies into the project.
A.Manage quality
B.Quality audit
C.Quality metrics
D.Quality improvement
軟考備考每日試題(230813)點(diǎn)擊跳轉(zhuǎn)
(230813)答案
66、67、【試題解析】
首先,成本最多63萬,超過63萬的方案需要排除。
畫出單代號(hào)網(wǎng)絡(luò)圖可知,關(guān)鍵路徑是ACD,工期12周,這是在正常進(jìn)度下。
如果全部趕工,關(guān)鍵路徑為AB或ACD兩條,工期8周,總費(fèi)用=8+15+17+13+11=64萬。超過總成本。
如果A不趕工,BCD全部趕工,關(guān)鍵路徑為AB或ACD兩條,工期9周。
總費(fèi)用=9+10+17+13+11=60萬元,符合總成本預(yù)算。
【參考答案】A、A
68、69、【試題解析】
本題考察資源平衡。
最短工期7天,最少配置10人,分配6人去完成乙工作,需要七天,再分配4人去完成丙工作需要2天,完工后,分配3人去完成甲工作。
【參考答案】B、C
70、【試題解析】
靜態(tài)投資回收期,不考慮時(shí)間價(jià)值,計(jì)算到什么時(shí)候?yàn)檎怠?/p>
-1200+(-1000)+200+300+500+500++500+200=0。
也就是說,第八年現(xiàn)金流為200的時(shí)候完成回收期,200/500=0.4,第八年只需要0.4年即可,7+0.4=7.4。
【參考答案】C

PDMA-NPDP?新產(chǎn)品開發(fā)專業(yè)人士認(rèn)證
PMI-PgMP?國際項(xiàng)目集管理認(rèn)證
PMI-PMP?國際項(xiàng)目管理認(rèn)證
信息系統(tǒng)項(xiàng)目管理師(軟考高項(xiàng))認(rèn)證
系統(tǒng)集成項(xiàng)目管理工程師(軟考中項(xiàng))認(rèn)證
項(xiàng)目管理專業(yè)人員能力評(píng)價(jià)(CSPM)
PMI-ACP?國際敏捷項(xiàng)目管理認(rèn)證
信息技術(shù)應(yīng)用創(chuàng)新人才評(píng)價(jià)(信創(chuàng)證書)