6、下列關于風險管理的說法哪種是正確的?
A、消極風險應該被定量,積極風險應該被定性
B、識別出來的風險應該加入風險登記冊
C、所有已知的風險都應該開列在風險管理計劃當中
D、不能被減輕的風險都應該被避免
7、A project manager has been assigned to implement new server equipment into a data center.Through a risk workshop,the following two risks have been identified and assessed as highly likely to occur.
1.Equipment is delayed due to shortages of key components.
2.The customer has not initiated preparation of the data center,risking a delay in the project.
What should the project manager do next?
一位項目經(jīng)理已被任命在一個數(shù)據(jù)中心安裝新的服務器設備。通過一次風險專題會,以下兩項風險已被識別,并被評估為發(fā)生的可能性高∶
1.由于關鍵部件短缺,導致設備延期。
2.客戶還未開始準備數(shù)據(jù)中心,導致項目延期。
項目經(jīng)理下一步應該做什么?()
A、Initiate the risk mitigation process
啟動風險減輕過程
B、Conduct a Monte Carlo analysis
執(zhí)行蒙特卡洛分析
C、Add to the risk management plan
添加進風險管理計劃
D、Initiate risk response planning
8、在一個復雜項目中,項目經(jīng)理困擾于大量文件,以及如何用最佳方法分發(fā)這些文件,項目經(jīng)理查詢下列哪—項?
A、項目管理信息系統(tǒng)(PMIS)。慧翔天地
B、配置管理系統(tǒng)。慧翔天地
C、項目相關方溝通需求。慧翔天地
D、績效報告和問題日志。慧翔天地
9、在一個復雜的長期項目上,項目經(jīng)理采用一種方法,詳細規(guī)劃近期工作,并在更高的層次規(guī)劃未來工作,這描述的是什么?
A、分解
B、滾動式規(guī)劃
C、解決方案行動規(guī)劃
D、調整時間提前量和時間滯后量
10、Due to outstanding issues,the project manager is concerned about the viability of the project.What should the project manager do next?()
由于還有未解決的問題,項目經(jīng)理十分擔心項目的可行性。項目經(jīng)理接下來應該怎么做?()
A、Communicate the issues to management向管理層溝通問題
B、Explore various solutions to the issue探討問題的不同解決方案
C、Create change requests創(chuàng)建變更請求
D、Document and quantify the risks and communicate it t o stakeholders記錄并量化風險,并與相關方溝通
(240503)答案
1、C
2、A
3、A
4、A
5、D