1、Which of the following describes the amount of individual re sources required for an existing schedule during specific time periods?
下列哪一項描述了現有進度表的特定時間段內對個別資源的需求量?
A、Resource histogram資源直方圖
B、Resource loading資源負荷
C、Resource leveling資源平衡
D、Resource planning資源規劃
2、A project has specific service level agreements which assure quality of service to the customer what tool can the project manager use to determine that the service is stable or has a predictable performance?
一個項目都有特定的服務水平協議,以保證對客戶的服務質量。項目經理應使用什么樣的工具,來確定該服務的穩定性,以及他的可預測性?
A、Control charts控制圖
B、Pareto charts帕累托圖
C、Flow charting流程圖口一
D、Bench marking標桿對照
3、The actual expenditure of a project to date is US$850,000,of a US$900,000 total project budget.The current earned value is US$750,000.What is the status of the project?
某個項目到目前為止的實際支出是850,000美元嗎,項目總預算為900,000美元,當前掙值為750,000美元,項目的狀態是什么?
A、US$100,000 over budget超出預算100,000美元
B、US$5,000 under budget低于預算50,000美元
C、US$100,000 under budget低于預算100,000美元
D、US$50,000 over budget超出預算50,000美元
4、A project manager joins a project with high-level requirements that are likely to change.The pro1ect manager identifies that the statement of work(SOW)contains a rough budget estimate.What type of contract should the project manager suggest for this project?
項目經理加入一個項目,該項目具有可能會發生變更的高層級需求.項目經理識別到工作說明書(SOW)包含一個粗略的預算估算.項目經理應該為該項目選擇以下哪一項合同?
A、Cost plus award fee(CPAF)成本加獎勵費用合同(C PAF)仔一
B、Fixed price with economic price adjustment(FP-EPA)總價加經濟價格調整合同(FP-EPA)
C、Time and material(T&M)工料合同(T&M)
D、Fixed price incentive fee(FPIF)總價加激勵費用合同(FPIF)
5、A few weeks after a project to develop a new project begins,local community advocates disrupt project work.What should the project manager do?
一個項目是為了開發一個新產品.在該項目開始幾周后;當地社區煽動破壞項目工作。項目經理應該做什么?
A、Ask the project sponsor to engage with local community groups to explain the project's benefits.要求項目發起人與當地社區團體接洽.解釋項目的收益。
B、Add the community as stakeholders in the stakeholder engagement plan.將該社區作為相關方添加進相關方參與計劃中。
C、Obtain legal assistance in regaining control of the project.獲取法律援助以重新獲得項目控制權。
D、Advise the community that their local representatives must be contacte.告知社區必須聯系他們的當地代表。
(250305)答案
6、B
7、A
8、B
9、B
10、A