6、Who participates in the change control board?
A.Project manager
B.Functional managers
C.Stakeholders
D.Project manager and functional managers
6、下列選項中,誰將參與變更控制委員會?
A.項目經理
B.職能經理
C.項目干系人
D.項目經理和職能經理
7、A project manager would like to evaluate the various factors that influence efficiencies in a production line.Which of the following tools should be used to evaluate systematically all key factors having the most influence on the overall outcome of the project
A.Pareto analysis
B.Benchmarking
C.Design of experiments
D.Cost-benefit analysis
7、項目經理想要評估影響生產線效率的各種因素。若要系統性的評估對項目總體成果最有影響的所有關鍵因素,應使用下列哪一項工具?
A.帕累托分析
B.標桿對照
C.實驗設計
D.成本-效益分析
8、If the end date of an initial plan is later than the desired date,what is the FIRST action the project manager should consider?
A.Reviewing current resource on the project
B.Determining whether more work can be done in parallel
C.Starting critical path activities at their early start dates.
D.Negotiating a change in scope for an activities with negative float
8、如果初步計劃的完工日期遲于期望日期,則項目經理應考慮的第一步行動是什么?
A.評審當前的項目資源情況
B.確定是否有更多工作能夠并行
C.在最早開始日期開始關鍵路線活動
D.為任何負時差活動協商工作范圍變化
9、Management tells a project manager to subcontract part of the project to a company that management has worked with many times.Under these circumstances,the project manager should be MOST concerned about:
A.making sure the company has the qualifications to complete the project.
B.meeting management’s expectations of time.
C.the cost of the subcontracted work.
D.the terms and conditions of the contract.
9、管理層告訴項目經理外包一部分項目給一公司,該公司與管理層合作過很多次。在這種情況下,項目經理最應該關心的是
A,確保該公司有資格完成該項目
B,滿足管理層的時間預期
C,外包工作的成本
D,合同條款
10、A buyer has negotiated a fixed-price incentive contract with the seller.The contract has a target cost of$200,000,a target profit of$30,000,and a target price of$230,000.The buyer has also negotiated a ceiling price of$270,000 and a share ratio of 70/30.If the seller completes the contract with actual costs of$170,000,how much profits will the buyer pay the seller?
A.$21,000
B.$35.000
C.$39.000
D.$51.000
10、目前有兩家公司要簽署一個固定價格加激勵費用的合同。雙方已經談妥合同的目標成本是200,000美元,目標費是30,000美元,因此合同的目標價格是230,000美元。買方還設定了270,000美元的最高價以及“七三開”的分成比率。如果賣方以170,000美元的實際成本完成了合同,除了合同的成本外,買方還要付給賣方多少費用
A,21,000美元
B,35,000美元
C,39,000美元
D,51,000美元
(211029)答案
1、C
2、B
3、B
4、C
5、A