1、在執(zhí)行一個(gè)實(shí)施法規(guī)變更的項(xiàng)目時(shí),根據(jù)專(zhuān)業(yè)技術(shù)專(zhuān)家的建議,項(xiàng)目經(jīng)理發(fā)現(xiàn)新流程不符合法規(guī)指導(dǎo)方針。一個(gè)項(xiàng)目變更要額外的資源,否則項(xiàng)目會(huì)受到負(fù)面影響。項(xiàng)目經(jīng)理首先應(yīng)∶
A、更新質(zhì)量管理計(jì)劃
B、評(píng)估變更并提交變更的資源計(jì)劃以供批準(zhǔn)
C、修改溝通管理計(jì)劃
D、執(zhí)行成本效益分析
2、項(xiàng)目中質(zhì)量審計(jì)的主要目標(biāo)是確定下列哪一項(xiàng)?
A、識(shí)別良好及最佳實(shí)踐
B、項(xiàng)目進(jìn)度變更
C、項(xiàng)目可交付成果的缺陷
D、項(xiàng)目范圍的偏差
3、一名監(jiān)控流程的項(xiàng)目團(tuán)隊(duì)成員正在查看控制圖,有六個(gè)連續(xù)的點(diǎn)低于平均值,但都在控制限制范圍內(nèi)。項(xiàng)目經(jīng)理應(yīng)該采取下列哪些行動(dòng)?
A、調(diào)整流程
B、創(chuàng)建石川圖
C、執(zhí)行實(shí)驗(yàn)設(shè)計(jì)
D、不需要采取任何行動(dòng)
4、項(xiàng)目發(fā)起人實(shí)施一項(xiàng)新的文件控制流程。這項(xiàng)新流程會(huì)延遲對(duì)信息的訪(fǎng)問(wèn),從而導(dǎo)致人工成本增加以及進(jìn)度延遲。項(xiàng)目經(jīng)理應(yīng)該如何執(zhí)行這個(gè)新過(guò)程?()
A、使用變更管理計(jì)劃實(shí)施新的需求
B、提出更為有效的文件控制流程用于項(xiàng)目
C、使用風(fēng)險(xiǎn)管理計(jì)劃評(píng)估風(fēng)險(xiǎn)
D、與項(xiàng)目相關(guān)方安排一次會(huì)議,進(jìn)行風(fēng)險(xiǎn)緊迫性評(píng)估
5、The project manager leads a development project for the customer.The project is externally funded with a strict payment plan and deadline.During the project execution phase.the project manager identifies that the project is behind schedule.What should the project manager do?
項(xiàng)目經(jīng)理接管客戶(hù)一個(gè)發(fā)展良好的項(xiàng)目。該項(xiàng)目是一個(gè)由外部資助的項(xiàng)目,實(shí)行嚴(yán)格的付款計(jì)劃和期限。在項(xiàng)目實(shí)施階段,項(xiàng)目經(jīng)理確定該項(xiàng)目工期落后了,此時(shí)項(xiàng)目經(jīng)理應(yīng)該怎么做?
A、Perform schedule compression to reach the determined deadline.把進(jìn)度壓縮到完工的最后期限。
B、Issue a change request and approve it with the customer.提交變更請(qǐng)求,請(qǐng)客戶(hù)批準(zhǔn)。
C、Take no action,since the contract does not identify penalties for late product deliverables.不采取任何行動(dòng),因?yàn)楹贤荒苊鞔_產(chǎn)品延遲交付的日期。
D、Decrease the number of quality audit to make the deli very on time.為準(zhǔn)時(shí)交付產(chǎn)品而實(shí)施質(zhì)量審計(jì)。
PMP備考每日試題(221219)點(diǎn)擊跳轉(zhuǎn)
(221219)答案
6、D
7、D
8、B
9、C
10、B

PDMA-NPDP?新產(chǎn)品開(kāi)發(fā)專(zhuān)業(yè)人士認(rèn)證
PMI-PgMP?國(guó)際項(xiàng)目集管理認(rèn)證
PMI-PMP?國(guó)際項(xiàng)目管理認(rèn)證
信息系統(tǒng)項(xiàng)目管理師(軟考高項(xiàng))認(rèn)證
系統(tǒng)集成項(xiàng)目管理工程師(軟考中項(xiàng))認(rèn)證
項(xiàng)目管理專(zhuān)業(yè)人員能力評(píng)價(jià)(CSPM)
PMI-ACP?國(guó)際敏捷項(xiàng)目管理認(rèn)證
信息技術(shù)應(yīng)用創(chuàng)新人才評(píng)價(jià)(信創(chuàng)證書(shū))